Bitget2026/09/29 02:26- Gold Hunter Resources issued a correction to earlier disclosures on its 2026 Great Northern drilling program funding, scope, permits, and contractors.
- Program ended at 2,879 meters on Sept. 4 when spending hit a fixed budget, not because it was funded to complete 10,000 meters.
- Budgeted drill spend was about 3.8 million, not the 6.7 million financing previously cited as tied to full program funding.
- Thor Deposit drilling was deferred to 2027 due to access-road bridge safety issues and outstanding repair permits.
- Company clarified it used Forage Fusion alongside MCL Drilling for helicopter-supported work earlier in the season.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Besent “Extinguishes Fire”: Rising US Treasury yields are a global phenomenon, dismisses concerns over AI bubble
U.S. Treasury Secretary Janet Yellen defended the rise in U.S. Treasury yields, stating that this increase is a global phenomenon rather than unique to the United States, and does not warrant excessive concern. She partially attributed inflationary pressures to higher oil prices caused by the Iran conflict, and expects the energy shock to subside as hostilities ease. Yellen refuted the notion of an AI bubble, arguing that investments by major tech companies are grounded in solid business logic.
Bitcoin Crash Warning Goes Viral as X Post Flags Benner Cycle

"New High" WLD rises to $0.6177, reaching a nearly 3-month peak