Reuters2026/09/09 10:47- Salazar flagged steady construction progress at Ecuador’s Curipamba-El Domo polymetallic mine, targeting commissioning in July 2027.
- Salazar holds a 25% carried interest to production; Silvercorp operates the project with a 75% stake.
- Cumulative capex reached USD 66.2 million through June 30, 2026; USD 12.3 million was spent in the three months ended June 30.
- Silvercorp drew USD 43.9 million on July 31 under a USD 175.5 million Wheaton stream, lifting total proceeds to about USD 87.8 million.
- Updated economics show after-tax NPV of USD 573 million at 8% discount; IRR 45%; initial capex USD 283.7 million.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Japan’s largest opposition party disbands! Political resistance faced by Sanae Takaichi decreases sharply, but expansionary fiscal policy is constrained by the ‘red line’ of the bond market
Japan's largest opposition party has effectively split. As Prime Minister Sanae Takaichi approaches one year in office and continues to strengthen her position, there will no longer be a unified force within the powerful House of Representatives to provide effective checks and balances against her.

Montega raises Sto price target to EUR 150, keeps buy rating
Block applies for a national trust bank license to custody BTC and stablecoins
Chewy's Fiscal Q2 Adjusted Earnings, Net Sales Rise