Denison Mines starts full-scale construction at Phoenix ISR uranium project in Saskatchewan
Reuters2026/08/14 16:25- Denison reported Q2 2026 progress at the Phoenix ISR uranium mine, with full-scale construction under way following site preparation since March.
- Over 20% of overall site civil work was completed by end-July; freeze wall installation for Phase 1 has started.
- Sold 750,000 pounds U3O8 at an average realized price of $122.16 per pound, generating $91.6 million in gross proceeds.
- Realized gain totaled $64.1 million, or 233%, versus the 2021 acquisition cost of $36.67 per pound.
- Held about 1.1 million pounds U3O8 at June 30; 600,000 pounds committed for delivery from Q3 2026 to Q2 2027.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like
Will a 10-year US Treasury yield rising to 5.5% "attack" US stocks? Societe Generale warns: this could be the valuation tipping point.
Bokobza, Global Head of Asset Allocation at Société Générale, pointed out that if the 10-year U.S. Treasury yield reaches 5.5%, corporate profit growth will not be sufficient to offset the impact of rising rates on valuations, and the stock market will face substantial pressure. However, he believes that the upcoming rate hikes by the Federal Reserve and the European Central Bank will be relatively limited and will not disrupt the current economic cycle.
The Dream of Big Profits in These Altcoins Didn’t Come True: Only 229 Users Managed to Earn $10,000! Here Are the Details
XRP Stuck in Range as $1.50 Breakout Level Comes Into Focus

Cilo Cybin publishes integrated annual report for year ended March 31, 2026