Eco Wave Power advances 1 MW Portugal wave energy project as APDL starts Barra do Douro breakwater repairs
Reuters2026/08/13 12:32- Eco Wave Power advanced its planned 1 MW onshore wave energy project in Porto as APDL began rehabilitating the Barra do Douro breakwater.
- Works follow storm damage, affecting the coastal infrastructure designated for the installation, with timing now tied to breakwater completion.
- CEO Inna Braverman will meet APDL in mid-August to align the completion schedule with installation readiness for the first phase.
- APDL agreed to issue a support letter for a request to extend the grid-connection deadline for the 1 MW phase.
- The APDL agreement allows development of up to 20 MW in Portugal, with the 1 MW installation positioned as the initial step.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like

Spot bitcoin ETFs pull in $987 million last week as institutional demand recovers
Silver Price Forecast: XAG/USD dips below $66.00 and hints at a bearish “H&S”
Twice thwarted in a week! Novartis (NVS.US) fails in phase III trial for blockbuster heart disease drug, stock plummets; Amgen (AMGN.US) dragged down as well
Swiss pharmaceutical giant Novartis has suffered another clinical trial setback—within one week, the company’s second major drug candidate has failed in a late-stage study. This latest disappointment concerns its potential blockbuster heart disease drug pelacarsen.